[Nut-upsuser] initial configuration assistance, fixed

Doug Parsons doparsons at earthlink.net
Thu Feb 1 02:15:38 CET 2007


> serial cable right! Now, onto the finer details of event configuration
> and working out exactly how to deal with our dual-PSU servers supplied by 
> different UPS: Some work ahead for me.

Good to hear that you got things going. As for the dual supply servers on 
two ups units, this is what lead me to use Nut in the first place. The docs 
discuss this setup:

http://www.networkupstools.org/doc/2.0.1/data-room.html

The main thing you need to make sure of is that your server does not freak 
when it looses power on one unit. We had some ML370 Compaq servers that 
would boot and run on one supply but if the server booted with all three 
supplies (yes three) plugged in and the one plug was pulled the server would 
shut off. Our dual unit servers seem to be fine loosing one supply (DL380) 
as I have moved the servers between UPS units by moving one plug at a time.

In my scenario I used one server (actually a virtual server) to monitor all 
20+ UPS units and then let the servers talk to it for status.

Doug 