[Nut-upsuser] NUT Client shuts down when performing runtime calibration on APC UPS
    Roger Price 
    roger at rogerprice.org
       
    Tue Dec 20 14:52:19 UTC 2016
    
    
  
On Tue, 20 Dec 2016, Merk - Oliver wrote:
> Last week I need to change the battery pack and then I needed to perform 
> a runtime calibration. I used the web interface of the AP9630 card to 
> start the runtime calibration. However, after 2min. of runtime 
> calibration the SAN shut down!
>
> This is because the UPS status goes "On Battery" during runtime 
> calibration and this is the signal for NUT to shut down the Client.
Out of curiosity : Is there any difference between the output of command 
"upsc my-ups" during a runtime calibration and during a wall power 
failure?  Specifically, is there any difference between the ups.status 
values?
Roger
    
    